ANSWER: A
References: PMBOK Guide, 4th Edition, page 102; Tom Kendrick, Identifying and Managing Project Risk: Essential Tools for Failure-Proofing Your Project, page 323
Keyword(s):
:

ANSWER: A
Reference: The reviewed person will regard the assessment process as fair and developmental.

Reference: Managing Project Quality by Timothy J. Kloppenborg and Joseph A. Petrick, page 66

Keyword(s):
:
ANSWER: B
Reference: PMBOK Guide 4th Edition, page 214.
Keyword(s):
:
ANSWER: D
PMBOK Guide 4th Edition, page 190.
Keyword(s):
:
ANSWER: D
A procurement audit is a structured review of the procurement process originating from Plan Procurements process through Administer Procurements process. This is one of the tools and techniques used in Close Procurements process. Reference: PMBOK(r) Guide Fourth Edition, Page Number:336 and 343
Keyword(s):
:
ANSWER: D
Reference: PMP: Project Management Professional Study Guide, by Kim Heldman, Claudia Baca and Patti Jansen, Deluxe Edition, pages 449-452
Keyword(s):
:
ANSWER: C
When closing the project, the project manager will review all prior information from the previous phase closures to ensure that all project work is complete and that the project has met its objectives. Reference: PMBOK(r) Guide Fourth Edition, Page 99
Keyword(s):
:
ANSWER: A
Reference: Project Management JumpStart by Kim Heldman, page 268
Keyword(s):
:
ANSWER: B
Option B: Since this is a "minor flaw," but rectification of that flaw would take a long time, it is better to discuss with the sponsor and customer and get their inputs Option A and Option D: This is unethical - the project manager should definitely complete the project as per the specifications before closing the project. Option C: Rectification of a minor flaw can lead to delay of 2 months in the project: so, the project manager should first inform the sponsor and customer before rectification of the flaw.
Keyword(s):
:
ANSWER: B
Reference: PMBOK Guide 4th Edition, pages 99-102.
Keyword(s):