Printer-friendly version
A collection of commonly asked questions, with answers, about a specific subject, assembled in a conveniently organized list for easy reading.


All Categories

Page:  1  2  3  4  5  6  7  8  9  10  11  (Next)
  ALL

DURING THE EXAM

:
The PMP examination consists of 200 multiple-choice questions, 25 of which are pretest questions used to develop future versions of the exam.

Pretest Questions:

* Are "trial" questions.
* Are used in examinations as an effective and legitimate way to test the validity of future examination questions.
* Do not affect the score.
* Are randomly placed throughout the exam.
Keyword(s):

PMBOOTCAMP.ORG

:

PMBootCamp contains thousands of PMP exam questions structured into a number of cumulative practice exams, along with targeted practice tests focused on individual PMBOK Project Management Processes (like real exam).

All 5 PMBOK Project Management Process Groups, including the Professional and Social Responsibility and PreTest questions are represented in our exam content. Your performance will be tracked and analyzed based on the groups below, allowing you to pinpoint areas which require more study.

Initiating Process Group

Planning Process Group

Executing Process Group

Monitoring and Controlling Process Group

Closing Process Group

Professional and Social Responsibility

PreTest Questions

Keyword(s):

PMP WISDOM

:
ANSWER: A PMBOK Guide 4th Edition, pages 73 and 284.
Keyword(s):
:
ANSWER: C
Expert judgment. Although (B) is somewhat true, expert judgment is a more correct answer; it is the knowledge of the product and how to decompose it that helps us identify the work more completely. PMBOK Guide Guide Fourth, Chapter 5
Keyword(s):
:
ANSWER: A
A standard. Framework Chapter 1 Choice 'b' a regulation, is a requirement imposed by a governing body. Choice 'c' a preferred approach, is similar to a best practice. Choice 'd' a specification, is a document that specifies how a deliverable will be measured for completeness.

Keyword(s):
:
ANSWER: C
Stakeholder management strategy. All other selections are tools and techniques, not outputs. PMBOK Guide Fourth Edition, Chapter 10, Section 10.1.3
Keyword(s):
:
ANSWER: C
Programs are a collection of projects with a common cause. A is incorrect because a program is a collection of projects, not just one large, complex project. B is incorrect because programs are not made up of just small projects. D is incorrect since projects with a common customer do not necessitate a program.
Keyword(s):
:
ANSWER: B
Reference: PMBOK Guide 4th Edition, page 442.
Keyword(s):
:
ANSWER: B
This question can be tricky, especially if you have spent so much time studying that you have forgotten some good project management practices. A quick look at Rita's Process Chart in the PMP Exam Prep book might draw you to conclude that the FIRST thing would be to start planning. Wouldn't it be smart to make sure what you have in the initial project scope statement and project charter are clear and complete before moving on? This is why choice B is the best choice.
Keyword(s):
:
ANSWER: A
In a functional organization, the project manager has the least support for the project and has little authority to assign resources. Choices C and D are roles in a weak matrix organization.
Keyword(s):

Page:  1  2  3  4  5  6  7  8  9  10  11  (Next)
  ALL


Share |